Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?
A
3 days
B
4 days
C
6 days
✓ Official correct answer
D
8 days