Mathematics Medium
Question

A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?

A
37 ½ days
✓ Official correct answer
B
22 days
C
31 days
D
22 days

Community credibility

Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.

A
37 ½ days
Official option

No member explanations yet for this option.

B
22 days
Official option

No member explanations yet for this option.

C
31 days
Official option

No member explanations yet for this option.

D
22 days
Official option

No member explanations yet for this option.

Related Questions

Q
Probability of something in interest rate of XXX?
Medium · Mathematics
Q
80% of 700 = __________?
Medium · Mathematics
Q
P is 5 times as large as Q, the percent that Q is less than P is ____________?
Medium · Mathematics
Q
Who was Blaise Pascal?
Medium · Mathematics