A and B separately take 9 and 12 days. They work alternately with A starting first. How many days to finish the work?

A
42/4 days
B
41/4 days
✓ Official correct answer
C
55 days
D
None of these

Community credibility

Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.

A
42/4 days
Official option

No member explanations yet for this option.

B
41/4 days
Official option

No member explanations yet for this option.

C
55 days
Official option

No member explanations yet for this option.

D
None of these
Official option

No member explanations yet for this option.

Explanation

Each 2-day cycle does 1/9 + 1/12 = 7/36. After 5 cycles (10 days): 35/36 left. A needs (1/36)/(1/9) = 1/4 day more ⇒ total = 41/4 days.

Related Questions

Q
Probability of something in interest rate of XXX?
Medium · Mathematics
Q
80% of 700 = ________?
Medium · Mathematics
Q
If P is 5 times as large as Q, by what percent is Q less than P?
Medium · Mathematics
Q
Who was Blaise Pascal?
Medium · Mathematics