TayariHub
Mathematics NULL Medium
Question

A and B together finish a work in 30 days. They work 20 days, then B leaves and A finishes the rest in 20 more days. In how many days can A alone finish the work?

A
70
B
50
C
40
D
60
✓ Official correct answer

Community credibility

Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.

A
70
Official option

No member explanations yet for this option.

B
50
Official option

No member explanations yet for this option.

C
40
Official option

No member explanations yet for this option.

D
60
Official option

No member explanations yet for this option.

Explanation

Together rate = 1/30. In 20 days they do 2/3; remaining 1/3 takes A 20 days ⇒ A's rate = 1/60 ⇒ A alone needs 60 days.

Related Questions

Q
Probability of something in interest rate of XXX?
Medium · Mathematics
Q
80% of 700 = ________?
Medium · Mathematics
Q
If P is 5 times as large as Q, by what percent is Q less than P?
Medium · Mathematics
Q
Who was Blaise Pascal?
Medium · Mathematics