Question
A and B together finish a work in 30 days. They work 20 days, then B leaves and A finishes the rest in 20 more days. In how many days can A alone finish the work?
A
70
B
50
C
40
D
60
✓ Official correct answer
Community credibility
Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.
A
70
No member explanations yet for this option.
B
50
No member explanations yet for this option.
C
40
No member explanations yet for this option.
D
60
No member explanations yet for this option.
Explanation
Together rate = 1/30. In 20 days they do 2/3; remaining 1/3 takes A 20 days ⇒ A's rate = 1/60 ⇒ A alone needs 60 days.