A does a work in 30 days and B in 40 days. How many days do they need working together?

A
70 days
B
120/7 days
✓ Official correct answer
C
50 days
D
45 days

Community credibility

Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.

A
70 days
Official option

No member explanations yet for this option.

B
120/7 days
Official option

No member explanations yet for this option.

C
50 days
Official option

No member explanations yet for this option.

D
45 days
Official option

No member explanations yet for this option.

Explanation

Combined rate = 1/30 + 1/40 = 7/120 ⇒ time = 120/7 days.

Related Questions

Q
Probability of something in interest rate of XXX?
Medium · Mathematics
Q
80% of 700 = ________?
Medium · Mathematics
Q
If P is 5 times as large as Q, by what percent is Q less than P?
Medium · Mathematics
Q
Who was Blaise Pascal?
Medium · Mathematics