Question

If 6 men take 9 days to finish a work, how many men are needed to finish it in 3 days?

A
2 men
B
12 men
C
9 men
D
18 men
✓ Official correct answer

Community credibility

Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.

A
2 men
Official option

No member explanations yet for this option.

B
12 men
Official option

No member explanations yet for this option.

C
9 men
Official option

No member explanations yet for this option.

D
18 men
Official option

No member explanations yet for this option.

Explanation

Total man-days = 6 × 9 = 54. For 3 days: 54/3 = 18 men.

Related Questions

Q
Probability of something in interest rate of XXX?
Medium · Mathematics
Q
80% of 700 = ________?
Medium · Mathematics
Q
If P is 5 times as large as Q, by what percent is Q less than P?
Medium · Mathematics
Q
Who was Blaise Pascal?
Medium · Mathematics