P and Q finish a work in 20 and 12 days. P starts alone; Q joins after 4 days until the end. How long does the work last?

A
5 days
B
10 days
✓ Official correct answer
C
15 days
D
12 days

Community credibility

Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.

A
5 days
Official option

No member explanations yet for this option.

B
10 days
Official option

No member explanations yet for this option.

C
15 days
Official option

No member explanations yet for this option.

D
12 days
Official option

No member explanations yet for this option.

Explanation

P alone for 4 days does 1/5. Remaining 4/5 at combined rate 1/20 + 1/12 = 2/15 needs 6 days. Total = 10 days.

Related Questions

Q
Probability of something in interest rate of XXX?
Medium · Mathematics
Q
80% of 700 = ________?
Medium · Mathematics
Q
If P is 5 times as large as Q, by what percent is Q less than P?
Medium · Mathematics
Q
Who was Blaise Pascal?
Medium · Mathematics