TayariHub
Mathematics NULL Medium
Question

P finishes a work in 18 days and Q in 15 days. Q works for 10 days and leaves. How many days does P need alone for the rest?

A
8
B
6
✓ Official correct answer
C
4
D
2

Community credibility

Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.

A
8
Official option

No member explanations yet for this option.

B
6
Official option

No member explanations yet for this option.

C
4
Official option

No member explanations yet for this option.

D
2
Official option

No member explanations yet for this option.

Explanation

Q does 10/15 = 2/3. Remaining 1/3 takes P (1/3) × 18 = 6 days.

Related Questions

Q
Probability of something in interest rate of XXX?
Medium · Mathematics
Q
80% of 700 = ________?
Medium · Mathematics
Q
If P is 5 times as large as Q, by what percent is Q less than P?
Medium · Mathematics
Q
Who was Blaise Pascal?
Medium · Mathematics